A group of 60 Maryland landowners has asked the U.S. Supreme Court to take up their fight over a proposed electricity transmission line across northern Maryland, Maryland Matters reports.
The petition, filed Wednesday, November 4, challenges lower court rulings that allowed surveyors from PSEG Renewable Transmission onto private property to conduct field studies for the Maryland Piedmont Reliability Project, a proposed 67 mile line.
The landowners argue the company should not be allowed onto their land before it receives state approval to build the line. Their attorneys wrote that the federal appeals court let a private company enter property without first showing it holds the government power it claims, which they called a serious threat to property rights.
The landowners say the issue could keep coming up whenever out of state companies are chosen by federal regulators to build power lines. Their attorneys noted that the state’s Power Plant Research Program and utilities already operating in Maryland would have eminent domain authority to conduct such surveys.